Insitu and Boeing: New-Parts Prices for Refurbished Parts

Whistleblower Justice Network

In the Insitu and Boeing drone pricing settlement, Insitu agreed to pay $25 million to resolve allegations that it used new-parts costs to price military drone contracts while planning to supply cheaper recycled or refurbished parts. A former pricing executive’s complaint followed the alleged mismatch into inventory accounting, supplier purchases and cost certifications he said he could not verify.

Insitu was the Boeing-owned drone maker headquartered in Bingen, Washington. The Justice Department announced the settlement on January 12, 2021, over contracts to supply and operate unmanned aerial vehicles for the Navy and United States Special Operations Command. A former Insitu executive brought the False Claims Act whistleblower case, and the government joined it.

What the Government Alleged About New and Refurbished Parts

The government’s allegation concerned the costs Insitu presented when seeking the contracts. The Justice Department said Insitu entered into five Navy contracts and two Special Operations Command contracts between January 1, 2009, and December 31, 2017, all awarded without competition. The government alleged that Insitu knowingly obtained inflated prices by proposing costs for new parts and materials while planning to use, and actually using, less expensive recycled, refurbished, reconditioned or reconfigured parts.

That puts the company’s plans at the center of the pricing story. Government negotiators received a cost account built around new parts, while the company allegedly intended to perform with cheaper inventory. The alleged overcharge was already being built into the award. Taxpayers would pay the price negotiated from that account.

The distinction matters across defense contract pricing arrangements. When certified cost or pricing data are required, the pricing-data certificate addresses whether the factual inputs were accurate, complete and current when the price was agreed. It reaches the facts underneath an estimate, including information reasonably available elsewhere in the company. For someone preparing a proposal, access to those facts is the difference between checking the costs and repeating somebody else’s numbers.

Cost Certifications Without the Underlying Data

The whistleblower’s complaint alleged that the executive responsible for pricing, estimating and procurement financial analysis repeatedly sought the raw accounting data behind Insitu’s proposals. He said the company initially blamed deficient accounting systems for its inability to provide the information. According to the complaint, he refused to sign more than 100 cost certifications because he could not confirm the costs.

The complaint identified the accounting method behind his concern. Insitu allegedly built its cost-estimating relationship from inventory averages that mixed current costs with used components, surplus stock and other categories:

This methodology blurred current, accurate, and complete labor and material costs with used, refurbished, reconditioned, reconfigured, surplus, and excess components, assembly, installation, and test costs.

United States ex rel. O’Hara v. Insitu, Inc. and The Boeing Company, whistleblower complaint, paragraph 22

The alleged problem ran through the calculation. A proposal could carry a cost figure without showing which inventory, labor or assembly costs produced it. The executive’s account explains why the raw data mattered: he wanted to test the inputs behind the figure he was being asked to certify.

According to the complaint, Insitu’s chief financial officer or contracts director certified proposals. The executive also described developing a data warehouse to compile historical accounting and business-system information for pricing and financial analysis. He alleged that his replacement later closed the project, removing a source of cost verification. So, in his account, the prices got certified while the person in charge of pricing could not check them.

Returned Parts Went Back Into the New-Parts Inventory

According to the complaint, aircraft, equipment and unused excess parts came back to Insitu when a military location closed or a mission ended. The whistleblower alleged that government-owned equipment went to a separate facility, while unused excess items from Insitu-owned and operated systems returned to its inventory of new parts.

He alleged that the government received no adjustment for those returned items:

USG did not receive a rebate, credit, or future offset for the unused returned excess parts which had been priced as a part of the proposals.

United States ex rel. O’Hara v. Insitu, Inc. and The Boeing Company, whistleblower complaint, paragraph 58

According to the complaint, the inventory did not distinguish newly manufactured parts from recently returned unused items. Many returned parts then went into other government agreements or were sold directly to the government, with proposals priced for brand-new, never previously purchased parts. The whistleblower alleged that Insitu’s cost for the already-paid-for inventory was lower than the cost of buying from the original manufacturer.

Ownership and inventory records connect a part’s return from one mission to the cost claimed for another. A warehouse employee could recognize the returning stock, while a pricing employee could recognize the new-parts assumption in the proposal.

Model Conversions and Bulk Purchases Changed the Cost Story

The complaint also alleged that Insitu passed the cost of its inventory choices to the government. When it had a surplus of unwanted drone models and too few of the requested model, it allegedly dismantled the unwanted systems and rebuilt them into the requested version. The whistleblower said the conversion cost more than building the requested model in the first place, and the government paid the higher amount. The complaint tied the extra expense to Insitu’s inventory problem and to the price presented to its government customer.

Supplier quantities supplied another alleged route to inflated pricing. The complaint said Insitu quoted parts costs based on the quantity needed for a particular government contract, then bought larger quantities at lower unit prices. It alleged that the government price used the higher cost and that Insitu obtained a larger profit margin than it had disclosed. The useful comparison is between the supplier information available during pricing and the information the government received.

The Civil Settlement and the Whistleblower’s Share

The settlement resolved the government’s allegations about the Navy and Special Operations Command contract prices. The Justice Department announced a $4.6 million whistleblower reward from the recovery for the former executive who brought the qui tam case. The investigation brought together the Naval Criminal Investigative Service, Defense Contract Audit Agency and Defense Criminal Investigative Service, working with the Justice Department.

What an Insider Can See Behind a Government Price

The evidence behind a defense pricing allegation connects the proposed cost to what the business knew about its parts, inventory and suppliers. In the Insitu complaint, the executive’s access problem and the underlying cost calculations belonged to the same story. The request for raw data, the pricing method and the certification explain how the disputed information reached a government proposal.

The same broad pricing problem appears in L3 Technologies’ May 2025 settlement. L3 agreed to pay $62 million over allegations that it withheld current, complete and accurate labor, material and other manufacturing cost data in sole-source, fixed-price proposals for military receivers. Those allegations concerned what the contractor disclosed to obtain the price, just as Insitu’s settlement centered on the cost account used to obtain its drone contracts.

A whistleblower case under the False Claims Act can pay 15% to 30% of what the government recovers. If you know how a proposal was assembled, why particular inventory was used or which supplier costs were available, talk to our whistleblower experts about building a defense pricing case around that knowledge.

You Know the Costs Behind the Proposal

If the pricing file you worked on told a different story from the inventory or supplier records, speak with our whistleblower experts about that difference. We work alongside you to build the case around what the company knew and bring in defense contract pricing whistleblower lawyers who understand the negotiations behind the government’s bill. We stay beside you through the process, with your knowledge of how the numbers were produced at the center of the case.